Jackson Rd

Location of roadwork:
Jackson Rd between Jackson Industrial Dr and Myrtle Ave

Township:
Scio

When is the work being done:
July 15, 2024

Description of work:
Concrete Pavement Repairs

Impact on Traffic:
Intermittent Lane Closures

Funding Source(s):
Four-Year Road and Non-Motorized Path Millage, Michigan Transportation Fund (MTF)

Latest Updates

October 11, 2024 Project Update #11: Jackson Rd (Scio Twp)

On Thursday, October 10, 2024, the Washtenaw County Road Commission (WCRC) reopened all lanes on westbound Jackson Rd between Jackson Industrial Dr and Myrtle Ave in Scio Township.

This week, contractors completed tasks such as sawing and sealing pavement joints, restoring disturbed areas with topsoil and seeding, and applying pavement markings. Remaining work includes installing traffic signal devices and correcting pavement surface imperfections through diamond grinding, which will involve intermittent daytime lane closures.

Additionally, WCRC has informed the Ann Arbor post office that mail carriers can resume normal delivery locations starting Friday, October 11, 2024, leading to the removal of temporary mailboxes.

The WCRC will continue to send out updates as the project progresses. Have questions about the project? Contact Aaron Berkholz, Assistant Director of Engineering, at (734) 327-6648, or via email at [email protected]. 

Pictured above is the application of pavement markings on westbound Jackson Rd between Myrtle Ave and Jackson Industrial Dr in Scio Township. 

October 10, 2024 Lane Reopened: Jackson Rd (Scio Twp)

WHEN: Thursday, October 10, 2024

WHERE: Jackson Rd between Jackson Industrial Dr and Myrtle Ave in Scio Township

WHY: Concrete rehabilitation

BACKGROUND: On Thursday, October 10, 2024, the Washtenaw County Road Commission (WCRC) reopened the westbound lane of Jackson Rd between Jackson Industrial Dr and Myrtle Ave in Scio Township.

All lanes are open; however, the contractor is still performing a few punch list items.

CONTACT: If you have any questions concerning this work, please contact Aaron Berkholz, Assistant Director of Engineering, at (734) 327-6648, or via email at [email protected].

ISSUE DATE: 10/10/24

October 2, 2024 Project Update #10: Jackson Rd (Scio Twp)

The final placement of concrete pavement occurred the week of September 30th on Jackson Rd between Myrtle Ave and Jackson Industrial Dr in Scio Township. 

The newly placed concrete will need time to cure. The remaining work will include the sealing of pavement joints, surface corrections (diamond grinding), placement of traffic signal devices, pavement markings and restorations. 

WCRC expects the project to be complete in October.  

WCRC will continue to send out updates as the project progresses. Have questions about the project? Contact Aaron Berkholz, Assistant Director of Engineering, at (734) 327-6648, or via email at [email protected]. 

Pictured above remaining concrete poured on Jackson Rd between Myrtle Ave and Jackson Industrial Dr in Scio Township. 
September 25, 2024 Project Update #9: Jackson Rd Concrete Rehabilitation (Scio Twp)

On Monday, September 23, 2024, the Washtenaw County Road Commission (WCRC) closed several eastbound to westbound crossovers (Michigan left turns) along westbound Jackson Rd between Jackson Industrial Dr and Myrtle Ave in Scio Township. If a crossover is closed drivers should go to the next open crossover.

This week, the contractor is switching driveway access points at businesses in order to remove and replace concrete gaps and place new concrete curbs and gutters. Access will continue to be maintained at all businesses along westbound Jackson Rd.

The week of September 30th, the contractor will remove and replace the concrete pavement damaged by motorists a week ago.

WCRC will continue to send out updates as the project progresses. Have questions about the project? Contact Aaron Berkholz, Assistant Director of Engineering, at (734) 327-6648, or via email at [email protected].

Pictured above is sawing and sealing joints on Jackson Rd between Myrtle Ave and Jackson Industrial Dr in Scio Township.
September 23, 2024 Traffic Impact: Jackson Rd (Scio Twp)

WHEN: Monday, September 23, 2024

WHERE: Jackson Rd between Myrtle Ave and Jackson Industrial Dr. in Scio Township

WHY: Traffic impact: closing some crossover

BACKGROUND: On Monday, September 23, 2024, the contractor for the Washtenaw County Road Commission (WCRC) will close some eastbound to westbound crossovers (Michigan left turns) along westbound Jackson Rd between Jackson Industrial Dr and Myrtle Ave in Scio Township. If a crossover is closed just go to the next open crossover.

The traffic impact is expected to be in place until mid-October. However, all dates are tentative and subject to change due to weather conditions.

CONTACT: If you have any questions concerning this work, please contact Aaron Berkholz, Assistant Director of Engineering, at (734) 327-6648, or via email at [email protected].

ISSUE DATE: 09/23/24

September 17, 2024 Project Update #8: Jackson Rd Concrete Rehabilitation (Scio Twp)

On Monday, September 16, 2024, the Washtenaw County Road Commission (WCRC) reopened a lane on southbound Zeeb Rd approaching Jackson Rd in Scio Township. Two southbound lanes on Zeeb Rd are now open to traffic. The right turn only (curbside) lane onto westbound Jackson Rd will remain closed.

There will be a few quiet days as the new concrete pavement is curing and gaining strength on the north side lanes (next to the businesses) on Jackson Rd between Myrtle Ave and Jackson Industrial Dr. The contractor will return to seal the joints when the concrete pavement has sufficient strength.

WCRC will continue to send out updates as the project progresses. Have questions about the project? Contact Aaron Berkholz, Assistant Director of Engineering, at (734) 327-6648, or via email at [email protected].

Pictured above is concrete curing on Jackson Rd between Myrtle Ave and Jackson Industrial Dr in Scio Township.

September 16, 2024 Lane Reopens: Southbound Zeeb Rd ( Scio Twp)

WHEN: Monday, September 16, 2024

WHERE: Southbound Zeeb Rd approaching Jackson Rd in Scio Township

WHY: Traffic impact: lane reopened

BACKGROUND: On Monday, September 16, 2024, the Washtenaw County Road Commission (WCRC) reopened southbound Zeeb Rd approaching Jackson Rd. There are two lanes open for traffic.

CONTACT: If you have any questions concerning this work, please contact Aaron Berkholz, Assistant Director of Engineering, at (734) 327-6648, or via email at [email protected].

ISSUE DATE: 09/16/24

September 10, 2024 Traffic Impact Lane Reduction: Jackson Rd (Scio Twp.)

WHEN: Thursday, September 12, 2024

WHERE: Southbound Zeeb Rd approaching Jackson Rd in Scio Township

WHY: Traffic impact: lane reduction

BACKGROUND: On Thursday, September 12, 2024, the Washtenaw County Road Commission (WCRC) will reduce southbound Zeeb Rd approaching Jackson Rd to one lane. Traffic will be permitted thru the intersection and turning right from the same lane. This lane restriction is needed to protect the new concrete pavement from truck turning movements onto westbound Jackson Rd between Zeeb Rd and Jackson Industrial Dr in Scio Township. (see photo below)

The traffic impact is expected to last approximately five days. However, all dates are tentative and subject to change due to weather conditions.

TRAFFIC IMPACT PICTURE: All southbound traffic will be restricted to one lane on southbound Zeeb Rd approaching Jackson Rd in Scio Twp.
CONTACT: If you have any questions concerning this work, please contact Aaron Berkholz, Assistant Director of Engineering, at (734) 327-6648, or via email at [email protected].

ISSUE DATE: 09/10/24

September 10, 2024 Project Update #7: Jackson Rd Concrete Rehabilitation (Scio Twp)

The week of September 9th, the new concrete pavement is being constructed in the north side lanes (next to the businesses) on Jackson Rd between Myrtle Ave and Jackson Industrial Dr in Scio Township. Westbound traffic on Jackson Rd and business access will be maintained. However, based on the logistics of placing the new concrete, traffic delays will occur. 

Later this week, the WCRC will temporarily reduce southbound Zeeb Rd approaching Jackson Rd to one traffic lane. This lane restriction is needed to protect the new concrete pavement from truck turning movements onto westbound Jackson Rd. 

Once the new pavement is placed, the concrete will cure and gain strength, and then the contractor will seal the joints. The work schedule is dependent upon weather conditions. We appreciate the patience of the business owners, their customers, and the traveling public as we work to improve Jackson Rd. 

WCRC will continue to send out updates as the project progresses. Have questions about the project? Contact Aaron Berkholz, Assistant Director of Engineering, at (734) 327-6648, or via email at [email protected]. 

Pictured above is the new pavement in the north side lanes (next to the businesses) on Jackson Rd between Myrtle Ave and Jackson Industrial Dr in Scio Township. 
August 26, 2024 Project Update #6: Jackson Rd Concrete Rehabilitation (Scio Twp)

On Monday, August 26th, the WCRC contractor will be adjusting temporary traffic control, directing westbound Jackson Rd motorists to use the newly paved concrete lane (next to the boulevard island) between Myrtle Ave and Jackson Industrial Dr in Scio Township. Westbound traffic will be maintained in a single lane through the construction zone.

The week of August 26th, the contractor will begin removing the old concrete pavement in the north side lane and placing aggregate (stone) base. In the coming weeks, concrete curb and gutter and new concrete pavement will be constructed. The work schedule is dependent upon weather conditions.

Access to the businesses along Jackson Rd will continue to be maintained. Some driveways will be half-width and others will be completely closed (where another driveway can be used). We appreciate the patience of the business owners and their customers as we work to improve Jackson Rd.

WCRC will continue to send out updates as the project progresses. Have questions about the project? Contact Aaron Berkholz, Assistant Director of Engineering, at (734) 327-6648, or via email at [email protected].

Pictured above is the temporary traffic shift on Jackson Rd between Myrtle Ave and Jackson Industrial Dr in Scio Township
August 12, 2024 Project Update #5: Jackson Rd Concrete Rehabilitation (Scio Twp)

On Friday, August 9th, the contractor moved temporary signs and barricades, switching crossovers (“Michigan lefts”) for traffic traveling on Jackson Rd between Jackson Industrial Dr and Myrtle Ave in Scio Township. These crossovers are used by eastbound and westbound motorists to access businesses on the opposite side of the Jackson Rd boulevard. 

Last week, after the new concrete pavement had cured and gained sufficient strength, the contractor sawed and sealed the joints and swept the new pavement. The remaining old concrete in the westbound lane adjacent to the boulevard is now being removed. Placement of the new concrete pavement in these areas is planned for later this week, depending on weather conditions. 

WCRC will continue to send out updates as the project progresses. Have questions about the project? Contact Aaron Berkholz, Assistant Director of Engineering, at (734) 327-6648, or via email at [email protected].  

Pictured above is the sawing of a concrete pavement joint on a crossover and a closed crossover on Jackson Rd between Jackson Industrial Dr and Myrtle Ave in Scio Township. 
August 1, 2024 Project Update #4: Jackson Rd Concrete Rehabilitation (Scio Twp)

Our concrete rehabilitation project taking place on westbound Jackson Rd between Jackson Industrial Dr and Myrtle Ave in Scio Township is progressing well.  

Since the last update, the contractor has been able to substantially complete the removal of the old concrete pavement in one lane, place aggregate (stone) base, and construct concrete curb and gutter. The contractor is currently constructing the new concrete pavement in the lane removed. The contractor expects this work to continue for five days, depending on weather conditions. Once the new pavement has been placed, the concrete will need to cure to gain strength. The remaining old pavement “gaps” will then be removed and replaced with new concrete pavement. 

WCRC will continue to send out updates as the project progresses. Have questions about the project? Contact Aaron Berkholz, Assistant Director of Engineering, at (734) 327-6648, or via email at [email protected].     

Pictured above is the new concrete pavement being placed on Jackson Rd between Jackson Industrial Dr and Myrtle Ave in Scio Township 
July 23, 2024 Project Update #3: Jackson Rd Concrete Rehabilitation (Scio Twp)

The Washtenaw County Road Commission’s (WCRC) concrete rehabilitation project on Jackson Rd between Jackson Industrial Dr and Myrtle Ave in Scio Township is moving along!  

Since the last update, the contractor has started the removal of the existing concrete pavement and curb. Next, the contractor will prepare the aggregate (stone) base and concrete curb will be constructed. The construction of the new concrete pavement is planned to begin during the week of July 29th. 

Motorists can expect lane restrictions in the westbound lanes of Jackson Rd until mid-October. Motorists traveling through the work zone should be extra attentive to the crews onsite and trucks entering into and leaving the closed lane. 

WCRC will continue to send out updates as the project progresses. Have questions about the project? Contact Aaron Berkholz, Assistant Director of Engineering, at (734) 327-6648, or via email at [email protected] 

Pictured above is the concrete pavement removal taking place on Jackson Rd between Jackson Industrial Dr and Myrtle Ave in Scio Township. 
July 12, 2024 Lane Restrictions: Jackson Rd (Scio Twp)

WHEN: Monday, July 15, 2024

WHERE: Jackson Rd between Jackson Industrial Dr and Myrtle Ave in Scio Township

WHY: Concrete rehabilitation

BACKGROUND: On Monday, July 15, 2024, a contractor for the Washtenaw County Road Commission (WCRC) will begin a concrete rehabilitation project on Jackson Rd between Jackson Industrial Dr and Myrtle Ave in Scio Township.

The road will not be closed to traffic, but delays are likely due to lane restrictions in the westbound lanes of Jackson Rd. WCRC encourages motorists, emergency services and others to use an alternate route.

The work is expected to take approximately three months. However, all dates are tentative and subject to change due to weather conditions.

CONTACT: If you have any questions concerning this work, please contact Aaron Berkholz, Assistant Director of Engineering, at (734) 327-6648, or via email at [email protected].

ISSUE DATE: 07/12/24

July 9, 2024 Project Update #2: Jackson Rd Concrete Rehabilitation (Scio Twp)

Heads up Scio Township! The Washtenaw County Road Commission (WCRC) concrete rehabilitation project on Jackson Rd between Jackson Industrial Dr and Myrtle Ave will begin soon!  

On Monday, July 8, portable changeable message signs (electronic message boards) regarding the project start date were placed on Jackson Rd. Construction is expected to begin Monday, July 15. Lane restrictions will be in place starting July 15 in the westbound lanes of Jackson Rd.  

The first step of construction will be sawing and removing the existing concrete, curb and pavement sections. Based on the significant traffic volumes on Jackson Rd, motorists can expect delays in the area. 

WCRC will continue to send out updates as the project progresses. Have questions about the project? Contact Aaron Berkholz, Assistant Director of Engineering, at (734) 327-6648, or via email at [email protected] 

Pictured above is one of the four electronic message boards placed on Jackson Rd between Jackson Industrial Dr and Myrtle Ave in Scio Township. 
April 12, 2024 Project Update #1: Jackson Rd Concrete Rehabilitation (Scio Twp)

During the 2024 construction season, the Washtenaw County Road Commission (WCRC) plans to rehabilitate the concrete in the westbound lanes of Jackson Rd between Jackson Industrial Dr and Myrtle Ave in Scio Township. During construction, traffic will be maintained under lane restrictions in the westbound lanes. Access to the business along Jackson Rd will be maintained for workers and customers.  
 
Thank you to those who were able to attend our virtual public information meeting on Thursday, April 11, 2024. If you weren’t able to join us, click here to watch the meeting recording or check out the slide show. WCRC will send out updates as the project progresses.  
 
Questions about the project? Contact Aaron Berkholz, Assistant Director of Engineering, at (734) 327-6648, or via email at berkholza@wcroads.org.  

Pictured above is the project limits of the Jackson Rd Concrete Rehabilitation Project in Scio Township.
March 13, 2024 Virtual Public Meeting: Jackson Rd Concrete Rehabilitation (Scio Twp)

PROJECT: Jackson Rd Concrete Rehabilitation Project

WHEN: Thursday, April 11, 2024, at 12 p.m.

WHERE: Online: https://bit.ly/wcrcprojectmeeting

By Touchtone Phone: (929) 205-6099, Meeting ID: 879 2332 8754

WHY: The Washtenaw County Road Commission (WCRC) will hold a virtual project information meeting regarding the planned concrete rehabilitation project on Jackson Rd in Scio Township.

During construction, traffic on Jackson Rd between Jackson Industrial Dr and Myrtle Ave will be maintained under lane closures. The lane closures are expected to be in place for approximately two months, weather pending.

The virtual public meeting will be held via Zoom on Thursday, April 11, 2024, at 12 p.m. There will be a brief presentation followed by time for questions from the audience. A recording of the meeting will be posted to the project web page after the meeting.

Click here to learn more about joining the virtual meeting.

CONTACT: If you have any questions concerning this project, please contact Aaron Berkholz, Assistant Director of Engineering, at (734) 327-6648, or via email at [email protected].

WCRC will provide necessary reasonable auxiliary aids and services, such as signers for the hearing impaired and audiotapes or printed material being presented at the meeting, to individuals with disabilities upon a 5-business day notice. Individuals with disabilities requiring auxiliary aids or services should contact Tiffany Oliphant, communications manager, by phone (734) 327-6646 or by email [email protected].

ISSUE DATE: 03/13/24

March 12, 2024 Project Announcement: Jackson Rd Concrete Rehabilitation (Scio Twp)

The Washtenaw County Road Commission (WCRC) plans to rehabilitate the concrete pavement in the westbound lanes of the Jackson Rd Corridor, between Jackson Industrial Dr and Myrtle Ave in Scio Township.

The Jackson Rd Corridor is a major artery that connects communities and is crucial to moving goods and services throughout Washtenaw County. The Jackson Rd Corridor Pavement Rehabilitation project is funded, in part, by the current Four-Year County-wide Roads and Non-Motorized Millage and the Michigan Transportation Fund (MTF). The estimated construction cost is $1 million.

“This road improvement is necessary to preserve and maintain a highly relied upon primary road,” says Aaron Berkholz, WCRC Assistant Director of Engineering. “The benefit of this investment in the county infrastructure will be realized for many years to come.”

During construction, a WCRC contractor will close one westbound lane of Jackson Rd, between Jackson Industrial Dr and Myrtle Ave, at a time. Westbound traffic will be maintained in a single lane, adjacent to the lane under construction. Based on significant traffic volumes on Jackson Rd, motorists can expect delays in the area.

WCRC will host a virtual public information meeting regarding this project in Spring 2024. For more information visit the project web page here.

WCRC will alert the public with construction updates on the WCRC website. Sign up for WCRC project updates here.

For specific questions regarding this project, please contact Aaron Berkholz, Assistant Director of Engineering, at (734) 327-6648, or via email at [email protected].

Pictured is the current condition of Jackson Rd between Zeeb Rd and Myrtle Ave in Scio Township.
Contact information:
Aaron Berkholz
    • (734) 327-6648
Receive Updates on the Project
Subscribe to Project Updates