Project Update #4: Jackson Rd Concrete Rehabilitation (Scio Twp)

By August 1, 2024Uncategorized

Our concrete rehabilitation project taking place on westbound Jackson Rd between Jackson Industrial Dr and Myrtle Ave in Scio Township is progressing well.  

Since the last update, the contractor has been able to substantially complete the removal of the old concrete pavement in one lane, place aggregate (stone) base, and construct concrete curb and gutter. The contractor is currently constructing the new concrete pavement in the lane removed. The contractor expects this work to continue for five days, depending on weather conditions. Once the new pavement has been placed, the concrete will need to cure to gain strength. The remaining old pavement “gaps” will then be removed and replaced with new concrete pavement. 

WCRC will continue to send out updates as the project progresses. Have questions about the project? Contact Aaron Berkholz, Assistant Director of Engineering, at (734) 327-6648, or via email at [email protected].     

Pictured above is the new concrete pavement being placed on Jackson Rd between Jackson Industrial Dr and Myrtle Ave in Scio Township