Project Update #5: Jackson Rd Concrete Rehabilitation (Scio Twp)

By August 12, 2024Project Updates

On Friday, August 9th, the contractor moved temporary signs and barricades, switching crossovers (“Michigan lefts”) for traffic traveling on Jackson Rd between Jackson Industrial Dr and Myrtle Ave in Scio Township. These crossovers are used by eastbound and westbound motorists to access businesses on the opposite side of the Jackson Rd boulevard. 

Last week, after the new concrete pavement had cured and gained sufficient strength, the contractor sawed and sealed the joints and swept the new pavement. The remaining old concrete in the westbound lane adjacent to the boulevard is now being removed. Placement of the new concrete pavement in these areas is planned for later this week, depending on weather conditions. 

WCRC will continue to send out updates as the project progresses. Have questions about the project? Contact Aaron Berkholz, Assistant Director of Engineering, at (734) 327-6648, or via email at [email protected].  

Pictured above is the sawing of a concrete pavement joint on a crossover and a closed crossover on Jackson Rd between Jackson Industrial Dr and Myrtle Ave in Scio Township.