Our contractor has been making steady progress all fall on phase 2 of the Border-to-Border Pathway project along M-52 in Lyndon Township. They have been working on grading the pathway…
Sections 1 and 2 of Bridge #2 were delivered earlier today! We expect the next section to be delivered later this week. These deliveries are causing periodic, 15-20 minute long road…
Our contractors have now buttoned up the Chubb Road paving project for the winter. Unfortunately, we were unable to pave the top layer of asphalt on Chubb Road between the…
WHEN: Starting Wednesday, December 4, 2019 WHERE: Huron River Drive between Mast Road and Zeeb Road in Scio Township WHY: Non-motorized bridge delivery BACKGROUND: Starting Wednesday, December 4, 2019, the…
WHAT: Review planned improvements to US-12 and M-17 in Ypsilanti Township WHEN: Monday, December 16, 2019, 6:30 p.m. WHERE: New Covenant Missionary Baptist Church, 2345 Tyler Rd, Ypsilanti WHY: Representative…
WHEN: Effective Friday, November 15, 2019 WHERE: Saline-Milan Road between Judd Road and Willis Road in York Township WHY: Completion of bridge project BACKGROUND: On Friday, November 15, 2019, the…
As you know, we were very pleased to reopen Ann Arbor-Saline Road last Friday (one week ahead of schedule!). We have a little more cleaning up to do in this…
Unfortunately, our contractors have recently discovered an unexpected utility conflict on the Chubb Road paving project in Salem Township. This conflict must be resolved before the road project can resume….
WHAT: Dixboro Road Trail Phase II Public Information Meeting WHEN: Thursday, December 5, 2019, from 7 – 8 p.m. WHERE: Dixboro United Methodist Church, 5221 Church Road, Ann Arbor, MI…
Well, there’s nothing like 10+ inches of snow in November to slow down a bridge project. Yesterday’s storm, unfortunately, has delayed completion of some of the final items on the…