The roundabout is taking shape at the intersection of Scio Church Rd and Zeeb Rd in Lodi and Scio Townships. The contractor is constructing concrete curbs. Next steps will be to install the colored (red), stamped concrete in the…
During the end of July, the contractor working on behalf of the Washtenaw County Road Commission (WCRC) constructed the concrete curb and road approaches to the Cherry Hill Rd Bridge, between Gale Rd and Plymouth Rd, in Superior Township. The contractor has completed asphalt paving and installed guardrails. …
The Washtenaw County Road Commission (WCRC) contractor recently set the new box culvert into place on Warner Road between Jewell Road and Judd Road in York Township. The next step…
PROJECT: Dexter-Ann Arbor Rd Safety Improvement Project WHEN: Thursday, August 27, 2026, at 11 a.m. WHERE: Online: https://bit.ly/wcrcprojectmeeting By Phone: (929) 205-6099, Meeting ID: 879 2332 8754 WHY: The Washtenaw County Road Commission…
This week, the contractor working on behalf of the Washtenaw County Road Commission (WCRC) is continuing to place stone to prepare for curb installation at the intersection of Scio Church Rd and Zeeb Rd…
The contractor working on behalf of the Washtenaw County Road commission (WCRC) constructed a temporary access road for Jennings Rd within the construction site. Removal of the existing bridge on…
On July 22, 2026, the contractor working on behalf of the Washtenaw County Road Commission (WCRC) began milling (removing) the existing road surface on Holmes Rd between Ford Rd and US-12BR (Michigan Ave) in Ypsilanti Township. Once the milling was completed, the contractor…
The contractor working on behalf of the Washtenaw County Road Commission (WCRC) completed the shoulder restoration and pavement markings on State Rd between Michigan Ave (US-12) to Old State Rd in Pittsfield Township. WCRC crews thereafter installed the new permanent signage. …
This week, the contractor working on behalf of the Washtenaw County Road Commission (WCRC) began road excavation in preparation for the removal of the existing culvert on Warner Rd between Jewell Rd and Judd Rd in York…
During the middle weeks of July, the contractor working on behalf of the Washtenaw County Road Commission (WCRC), stripped forms for the bridge and is allowing the bridge deck to cure and gain strength. This week…
