Project Update #1: Dixboro Rd Resurfacing (Ann Arbor, Northfield, Salem, & Superior Twps)

By September 15, 2026Project Updates

A contractor for the Washtenaw County Road Commission (WCRC) completed re-paving on Dixboro Road between M-14 and Pontiac Trail on Monday, September 14, 2026. 

Crews began milling (removing) the surface on September 10 and finished laying the new asphalt, affecting parts of Ann Arbor, Northfield, Salem, and Superior Townships. The road is fully open, but drivers should remain cautious as contractors will return in the coming weeks to place aggregate shoulders and paint permanent pavement markings. 

If you have questions, contact   Felix Weber, Project Manager, (734) 327-6689, or via email at [email protected]. 

Pictured above is the contractor milling the surface of Dixboro Rd between M-14 and Pontiac Trail in Ann Arbor, Northfield, Salem, and Superior Townships. 
Washtenaw County Road Commission
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.