We’re paving our safety project taking place at the intersection of N. Territorial Rd & Webster Church Rd in Webster Township! Since the last update, the contractor placed the aggregate…
Our roundabout project at the intersection of Miller Rd & Zeeb Rd in Scio Township is progressing quickly. Since the last update, the contractor has been able to complete the…
The Washtenaw County Road Commission (WCRC) is announcing plans to invest $1.5 million to protect approximately 30 lane miles of pavement throughout Washtenaw County during the 2024 construction season with…
Our safety improvement project at the intersection of N. Territorial Rd & Dexter Town Hall Rd in Dexter Township has been delayed due to inclement weather. Heavy rainfall over the…
The D3 Segment of the Border-to-Border trail along the Huron River in Scio Township is starting to take shape! Since the last update, the contractor has been able to pour…
Our safety improvement project at the intersection of N. Territorial Rd & Webster Church Rd in Webster Township is moving along! Since the last update, the contractor has been able…
Things are moving along on the Miller Rd at Zeeb Rd Roundabout project in Scio Township! Since the last update, all curbs and sidewalks have been installed. The next step…
Great news! Over the weekend, the contractor was able to finish paving on Sharon Hollow Rd between Austin Rd and Sharon Valley Rd in Manchester & Sharon Townships. Aggregate (stone)…
Our resurfacing project on Sharon Hollow Rd between Austin Rd and Sharon Valley Rd in Manchester & Sharon Townships is moving along quickly! Since the last update, the contractor has…
Construction is moving along on the Miller Rd at Zeeb Rd Roundabout project in Scio Township. Since the last update, the contractor has been able to install the storm…