Things are moving along on the Miller Rd at Zeeb Rd Roundabout project in Scio Township!
Since the last update, all curbs and sidewalks have been installed. The next step is placing the stamped concrete in the center island, followed by the splitter islands. Once the concrete islands have been completed, asphalt paving will begin, which is scheduled for after the Memorial Day weekend.
As a reminder, the intersection of Miller Rd and Zeeb Rd remains CLOSED to the traveling public. Access will only be maintained for residents who live or work within the construction zone. The Washtenaw County Road Commission (WCRC) will continue to send out road updates as the project progresses.
Have questions? Contact Kevin Dubnicki, Project Manager – Design & Construction, (734) 327-6693, or via email at [email protected].