Great news! Over the weekend, the contractor was able to finish paving on Sharon Hollow Rd between Austin Rd and Sharon Valley Rd in Manchester & Sharon Townships.
Aggregate (stone) shoulders will be placed later this week. Once completed, all restrictions on Sharon Hollow Rd will be lifted. The schedule for pavement markings is still yet to be determined.
The Washtenaw County Road Commission (WCRC) plans to chip seal this segment of roadway later this construction season. This treatment will help protect and prolong the new asphalt that was placed.
Have questions regarding the project? Contact Mike Bernbeck, Project Manager – Design & Construction, (734) 327-6654, via email at [email protected].