Good afternoon, It’s been a busy week for the entire organization! Monday, the N. Territorial Rd and Webster Church Rd intersection in Webster Township, and the Miller Rd and…
TITLE: Jackson Road Concrete Pavement Inlay DEADLINE: Tuesday, May 14, 2024 BRIEF DESCRIPTION: The Jackson Road Project shall consist of all labor, materials, and equipment required for the proposed concrete…
WHEN: Thursday, April 18, 2024 WHERE: N. Territorial Rd between east of Scully Rd and Lori Lynn Ln in Webster Township WHY: Emergency road closure BACKGROUND: On Thursday, April 18,…
TITLE: 2024 Pedestrian Facilities Upgrades DEADLINE: Thursday, May 9, 2024, at 10:00 a.m. BRIEF DESCRIPTION: This project consists of targeted ramp and sidewalk upgrades per the Americans with Disabilities Act…
WHEN: Friday, April 19, 2024 WHERE: Jackson Rd between Staebler Rd and Jackson Industrial Dr in Scio Township WHY: Permit – utility work BACKGROUND: On Friday, April 19, 2024, 123NET…
WHEN: Thursday, April 18, 2024 WHERE: Austin Rd between Grossman Rd and Wald Strasse St in Manchester Township WHY: Culvert replacement BACKGROUND: On Thursday, April 18, 2024, the Washtenaw County…
Our Unpaved Road Improvement project on Joy Rd between Whitmore Lake Rd and Earhart Rd in Ann Arbor & Northfield Townships is moving along. Last week, our crews were able…
WHEN: Tuesday, April 16, 2024 WHERE: Liberty Rd between Honey Run Dr and Stag’s Leap in Scio Township BACKGROUND: On Tuesday, April 16, 2024, the Washtenaw County Road Commission (WCRC)…
During the 2024 construction season, the Washtenaw County Road Commission (WCRC) plans to rehabilitate the concrete in the westbound lanes of Jackson Rd between Jackson Industrial Dr and Myrtle Ave…
WHEN: Wednesday, April 17, 2024 WHERE: Parker Rd between Scio Church Rd and Liberty Rd in Lima & Scio Townships WHY: Drainage & forestry work BACKGROUND: On Wednesday, April 17,…