WHEN: On Wednesday, May 24, 2023 WHERE: Zeeb Rd between Scio Rd/Peters Rd and Huron River Dr in Scio Township WHY: Permit work: pedestrian pathway BACKGROUND: On Wednesday, May 24,…
WHEN: On Wednesday, May 24, 2023 WHERE: Hoppe Rd, just south of Garvey Rd at the railroad tracks, in Sylvan Township WHY: Emergency repair BACKGROUND: On Wednesday, May 24, 2023,…
Construction is going well on the D3 section of the Border-to-Border (B2B) Trail along the Huron River in Scio Township. Over the past few weeks, the contractor has been able…
WHEN: On Wednesday, May 24, 2023 WHERE: The southbound lane of Stony Creek Rd, just north of the Textile Rd roundabout, in Ypsilanti Township WHY: Permit work: utility work BACKGROUND:…
During the 2023 construction season, the Washtenaw County Road Commission (WCRC) plans to replace a culvert on Parker Rd between Shield Rd and Dexter-Chelsea Rd in Lima & Scio Townships….
WHEN: On Tuesday, May 23, 2023 WHERE: Bowdish Rd between Worden Rd and Roepke Rd in Lyndon Township WHY: Permit work: Consumers pipeline project BACKGROUND: On Tuesday, May 23, 2023,…
Construction is going well on the Textile Rd resurfacing project in Pittsfield & Ypsilanti Townships. Last week our contractor completed paving two phases of Textile Rd between Whittaker Rd and…
WHEN: On Monday, May 22, 2023 WHERE: Bemis Rd between Moon Rd and Warner Rd in Pittsfield Township WHY: Road resurfacing BACKGROUND: On Monday, May 22, 2023, the Washtenaw County…
Good afternoon, Construction on the Main Yard salt barn has begun! This week, our contractor has been removing sod and leveling the ground where the storage building will be constructed….
Good afternoon, What a week it has been! We have been busy on many fronts. Construction is in full swing both with engineering and operations projects. Routine maintenance such as…