On Thursday, May 15, 2025, PK Contracting, a contractor for the Washtenaw County Road Commission (WCRC), completed the installation of final pavement markings on 7 Mile Road between Earhart Road…
Monitoring the weather forecast closely and aiming to complete work ahead of anticipated rainfall, WCRC contractor accelerated paving operations on Tyler Rd between McGregor Road and Airport Road in Ypsilanti…
The week of May 12th, E.T. MacKenzie, the contractor for the Washtenaw County Road Commission (WCRC), closed Bemis Rd between Stony Creek Rd and Hitchingham Rd in Augusta and Ypsilanti…
The Tyler Road Reconstruction Project is on schedule. This week, the Washtenaw County Road Commission (WCRC) contractor is constructing concrete curb and spillways along the north and south sides of…
During the week of April 28, Cadillac Asphalt, the contractor working for the Washtenaw County Road Commission (WCRC), removed the top layer of asphalt on 7 Mile Rd between Earhart…
The Washtenaw County Road Commission (WCRC) Contractor is continuing to make progress on the Tyler Road project between McGregor Road and Airport Road in Ypsilanti Township. Recently, the Contractor connected…
The Washtenaw County Road Commission (WCRC) will resume work on the Bemis Rd paving project between Stony Creek Rd and Hitchingham Rd in Augusta and Ypsilanti Townships, now that the…
This week, WCRC’s contractor installed upgraded stormwater systems around the dam. WCRC also worked on upgrading drainage along Tyler Rd, North and East of the project site to divert flow…
This week, WCRC’s contractor focused on protecting the site from several rain events. The washout being repaired was caused by outdated stormwater collection systems, so the contractor reinforced the open…
This week, the contractor focused on demolition of the existing roadway, clearing the washout area, and removing the guardrail. They are also preparing to remove the abandoned utilities. In the…