Project Update #5 – Tyler Rd Reconstruction (Ypsilanti Twp)

The Washtenaw County Road Commission (WCRC) Contractor is continuing to make progress on the Tyler Road project between McGregor Road and Airport Road in Ypsilanti Township.

Recently, the Contractor connected the storm sewer system into the bridge structure to promote efficient drainage during rain events. This two-day operation involved careful drilling and close monitoring of the structural integrity of the bridge.

Construction crews also prepared the nearby slope (previously washed out) for a new erosion control system. This system includes a durable cellular grid to promote slope stability during heavy rain events. The slope work began on Wednesday, April 23.

Next week, the Contractor plans to begin constructing the road base and installing storm drainage spillways at the east end of the project.

WCRC will continue to send out updates as the project progresses. Have questions? Contact Neeko Robison, Project Manager – Design & Construction, (734) 327-6660, or via email at [email protected].

Pictured above: The Contractor tapping the Tyler Rd Bridge to outlet stormwater drainage under the bridge and installing slope stabilizing materials.