Sharon Hollow Rd

Location of roadwork:
Sharon Hollow Rd between Austin Rd and Sharon Valley Rd

Township:
Manchester, Sharon

When is the work being done:
2024

Description of work:
Mill & Resurfacing

Impact on Traffic:
Lane Restrictions and Flagging Operation

Funding Source(s):
Four-Year Road and Non-Motorized Path Millage, Michigan Transportation Fund (MTF)

Latest Updates

May 9, 2024 Project Update #2: Sharon Hollow Rd Resurfacing (Manchester & Sharon Twps)

Our resurfacing project on Sharon Hollow Rd between Austin Rd and Sharon Valley Rd in Manchester & Sharon Townships is moving along quickly!  

Since the last update, the contractor has been able to pave the southbound lane. Paving operations will pause today due to weather conditions. However, the contractor expects to begin paving the northbound lane on Friday, May 10. If the weather cooperates, the contractor expects to place aggregate (stone) shoulders by the beginning of next week. Once shoulders are in place, all traffic restrictions will be lifted.  

The Washtenaw County Road Commission (WCRC) will continue to send out updates as the project progresses.  

Have questions? Contact Mike Bernbeck, Project Manager – Design & Construction, at (734) 327-6654, or via email at [email protected] 

Pictured is the resurfacing project taking place on Sharon Hollow Rd between Austin Rd and Sharon Valley Rd in Manchester & Sharon Townships.  
May 7, 2024 Project Update #1: Sharon Hollow Rd Resurfacing (Manchester & Sharon Twps)

Our resurfacing project on Sharon Hollow Rd between Austin Rd and Sharon Valley Rd in Manchester and Sharon Townships is going well.  

Yesterday, the contractor was able to mill the existing road surface. Today, the expected rain will pause operations. On Wednesday, May 8, 2024, the contractor expects to begin paving the new road surface, which can take approximately two days to complete, pending weather conditions. Once paving is finished, aggregate (stone) shoulders and pavement markings will be placed.  

The Washtenaw County Road Commission (WCRC) will continue to send out updates as the project progresses.  

Have questions about the project? Contact Mike Bernbeck, Project Manager – Design & Construction, at (734) 327-6654, or via email at [email protected].    

Pictured is the milled surface of Sharon Hollow Rd between Austin Rd and Sharon Valley Rd in Manchester and Sharon Townships.  
May 1, 2024 Lane Restrictions: Sharon Hollow Rd (Manchester & Sharon Twps)

WHEN: Monday, May 6, 2024

WHERE: Sharon Hollow Rd between Austin Rd and Sharon Valley Rd in Manchester & Sharon Townships

WHY: Road resurfacing

BACKGROUND: On Monday, May 6, 2024, the Washtenaw County Road Commission (WCRC) will begin a resurfacing project on Sharon Hollow Rd between Austin Rd and Sharon Valley Rd in Manchester & Sharon Townships.

The road will not be closed to traffic, but delays are likely due to lane restrictions and a flagging operation. WCRC encourages motorists, emergency services and others to use an alternate route.

The road improvements are expected to take approximately two weeks. However, all dates are tentative and subject to change due to weather conditions.

CONTACT: If you have any questions concerning this work, please contact Mike Bernbeck, Project Manager – Design & Construction, (734) 327-6654, or via email at [email protected]

ISSUE DATE: 05/01/24

March 19, 2024 Virtual Public Meeting: 2024 Resurfacing Program (County-wide)

PROJECT: 2024 County-wide Resurfacing Program

WHEN: Thursday, April 4, 2024, at 11 a.m.

WHERE: Online: https://bit.ly/wcrcprojectmeeting

By Touchtone Phone: (929) 205-6099, Meeting ID: 879 2332 8754

WHY: The Washtenaw County Road Commission (WCRC) will hold a virtual project information meeting regarding the planned County-wide Resurfacing Program taking place during the 2024 construction season.

During construction, traffic will be maintained under lane restrictions and flagging operations. During specific construction activities, the road may be closed, and a detour will be posted. WCRC estimates it will take approximately two/three weeks, on average, to complete each project, weather pending.

The virtual public meeting will be held via Zoom Thursday, April 4, 2024, at 11 a.m. There will be a brief presentation followed by time for questions from the audience. A recording of the meeting will be posted to the project web page after the meeting.

Click here to learn more about joining the virtual meeting.

CONTACT: If you have any questions concerning this project, please contact Mike Bernbeck, Project Manager, at (734) 327-6654, or via email at [email protected].

WCRC will provide necessary reasonable auxiliary aids and services, such as signers for the hearing impaired and audiotapes or printed material being presented at the meeting, to individuals with disabilities upon a 5-business day notice. Individuals with disabilities requiring auxiliary aids or services should contact Tiffany Oliphant, communications manager, by phone (734) 327-6646 or by email [email protected].

ISSUE DATE: 03/19/24

March 15, 2024 Project Announcement: 2024 Resurfacing Program (County-wide)

The Washtenaw County Road Commission (WCRC) is announcing plans to invest $6.7 million to improve approximately 20 lane miles of pavement throughout Washtenaw County during the 2024 construction season. Cadillac Asphalt was awarded the contract. The projects are funded through the 2021-2024 Four-year County-wide Roads and Non-Motorized Millage, federal funds and Michigan Transportation Funds (MTF).

“Most of these investments are made possible by Washtenaw County residents who travel on these roads every day. As stewards of these precious dollars, WCRC is committed to ensuring these resources are reinvested into communities, in which it came from,” said Mike Bernbeck, WCRC Project Manager.

Construction will begin mid-April and will end during the fall of 2024, weather pending. Listed below are the project locations with a link to their project web page, funding cost and traffic impacts:

Motorists will experience road closures with detours, lane restrictions, and flagging operations. WCRC will maintain access for residents who live or work within the project limits during construction.

WCRC will host a virtual public information meeting regarding the County-wide Resurfacing projects in Spring 2024. WCRC will post project updates online at wcroads.org. Residents can subscribe to road work advisories and project updates here.

For specific questions on this project, contact Mike Bernbeck, Project Manager, (734) 327-6654 or [email protected].

Pictured is a map of our 2024 County-wide Resurfacing Program.

Contact information:
Mike Bernbeck
    • (734) 327-6654
Receive Updates on the Project
Subscribe to Project Updates