Miller Rd and Zeeb Rd

Location of roadwork:
intersection of Miller Rd and Zeeb Rd

Township:
Scio

When is the work being done:
Spring / Summer 2024

Description of work:
Roundabout

Impact on Traffic:
Road Closure with Detour

Funding Source(s):
Federal, Michigan Transportation Fund (MTF)

Latest Updates

April 24, 2024 Project Update #4: Miller Rd at Zeeb Rd Roundabout (Scio Twp)

Construction began last week on the Miller Rd and Zeeb Rd Roundabout project located in Scio Township!

Over the past week, the contractor has been successful in removing the existing pavement and grading a new road base. Currently, the contractor is working to install the storm sewer. This work will continue for the next week. Next, the contractor will begin backfilling of low areas of the proposed Roundabout in preparation of the road surface and placement of curb and gutter, which is expected to begin in a few weeks.

The intersection of Miller Rd and Zeeb Rd remains closed to the traveling public. Access will only be maintained for residents who live or work within the construction zone. The Washtenaw County Road Commission (WCRC) will continue to send out updates as the project progresses.

Have questions? Contact Kevin Dubnicki, Project Manager – Design & Construction, (734) 327-6693, or via email at [email protected].

Pictured is the installation of the storm sewer for the roundabout at Miller Rd and Zeeb Rd in Scio Township.
April 10, 2024 Road Closure with Detour: Intersection of Miller Rd & Zeeb Rd (Scio Twp)

WHEN: Monday, April 15, 2024

WHERE: Intersection of Miller Rd and Zeeb Rd in Scio Township

WHY: Roundabout construction

BACKGROUND: On Monday, April 15, 2024, the Washtenaw County Road Commission (WCRC) will close the intersection of Miller Rd and Zeeb Rd in Scio Township to construct a roundabout.

The road improvements are expected to take approximately 12 weeks. However, all dates are tentative and subject to change due to weather conditions and contractor scheduling.

DETOUR: Click here for the Miller Rd detour map. Click here for the Zeeb Rd detour map.

CONTACT: If you have any questions concerning this work, please contact Kevin Dubnicki, Project Manager – D & C, (734) 327-6693, or via email at [email protected]

ISSUE DATE: 04/10/24

March 28, 2024 Lane Restrictions: Intersection of Miller Rd & Zeeb Rd (Scio Twp)

WHEN: Friday, March 29, 2024

WHERE: Intersection of Miller Rd and Zeeb Rd in Scio Township

WHY: Road resurfacing

BACKGROUND: On Friday, March 29, 2024, a contractor for DTE Gas will begin utility work at the Intersection of Miller Rd and Zeeb Rd in Scio Township.

The road will not be closed to traffic, but delays are likely due to lane restrictions. WCRC encourages motorists, emergency services and others to use an alternate route.

The permit work is expected to take approximately five days. However, all dates are tentative and subject to change due to weather conditions.

CONTACT: If you have any questions concerning this work, please contact Kevin Dubnicki, Project Manager – D&C, (734) 327-6693, or via email at [email protected]

ISSUE DATE: 03/28/24

February 21, 2024 Road Reopened: Miller Rd (Scio Twp)

WHEN: Wednesday, February 21, 2024

WHERE: Miller Rd between Dexter-Ann Arbor Rd and Zeeb Rd in Scio Township

WHY: Completion of forestry work

BACKGROUND: On Wednesday, February 21, 2024, the Washtenaw County Road Commission (WCRC) re-opened Miller Rd between Dexter-Ann Arbor Rd and Zeeb Rd in Scio Township.

CONTACT: If you have any questions concerning this project, please contact Jared Powers, Asst. Superintendent of Maintenance, (734) 327-6650 or [email protected]

ISSUE DATE: 02/21/24

February 16, 2024 Project Update #3: Miller Rd at Zeeb Rd Roundabout (Scio Twp)

The Washtenaw County Road Commission (WCRC) plans to construct a roundabout at the intersection of Miller Rd and Zeeb Rd in Scio Township during the 2024 construction season. During construction, the intersection will be closed to all traffic and a detour will be posted. 

Thank you to everyone who attended our virtual public construction information meeting on Thursday, February 15, 2024. If you weren’t able to join us, click here to watch the meeting recording or check out the slide show. 

In preparation for this project, next week our contractor will begin removing a significant number of trees and performing forestry work. To ensure the safety of the workers and the public, WCRC will close Miller Rd between Dexter-Ann Arbor Rd and Zeeb Rd in Scio Township. WCRC will continue to post updates as the project progresses. 

Questions? Contact Kevin Dubnicki, Project Manager, at (734) 327-6693, or via email at [email protected] 

Pictured is the brush and trees that will be removed along Miller Rd between Dexter-Ann Arbor Rd and Zeeb Rd in Scio Township.
February 16, 2024 Road Closure with Detour: Miller Rd (Scio Twp)

WHEN: Monday, February 19, 2024

WHERE: Miller Rd between Dexter-Ann Arbor Rd and Zeeb Rd in Scio Township

WHY: Forestry

BACKGROUND: On Monday, February 19, 2024, the Washtenaw County Road Commission (WCRC) will close Miller Rd between Dexter-Ann Arbor Rd and Zeeb Rd in Scio Township to perform forestry work.

The roadwork is expected to take approximately five days. However, all dates are tentative and subject to change due to weather conditions.

DETOUR: Click here for the detour map.

CONTACT: If you have any questions concerning this work, please contact Jared Powers, Assistant Superintendent of Maintenance, (734) 327-6650, or via email at [email protected]        

ISSUE DATE: 02/16/24

January 18, 2024 Virtual Public Meeting: Miller Rd & Zeeb Rd Roundabout (Scio Twp)

PROJECT: Miller Rd at Zeeb Rd Roundabout Project

WHEN: Thursday, February 15, 2024, at 11 a.m.

WHERE: Online: https://bit.ly/wcrcprojectmeeting

By Touchtone Phone: (929) 205-6099, Meeting ID: 879 2332 8754

WHY: The Washtenaw County Road Commission (WCRC) will hold a virtual project information meeting regarding the planned roundabout at the intersection of Miller Rd and Zeeb Rd in Scio Township.

During construction, the intersection of Miller Rd and Zeeb Rd will be closed to ALL traffic and a detour will be posted. The closure is expected to be in place for approximately 10 weeks, weather pending.

The virtual public meeting will be held via Zoom Thursday, February 15, 2024, at 11 a.m. There will be a brief presentation followed by time for questions from the audience. A recording of the meeting will be posted to the project web page after the meeting.

Click here to learn more about joining the virtual meeting.

CONTACT: If you have any questions concerning this project, please contact Michele Ford, project manager, at (734) 327-6652, or via email at [email protected].

WCRC will provide necessary reasonable auxiliary aids and services, such as signers for the hearing impaired and audiotapes or printed material being presented at the meeting, to individuals with disabilities upon a 5-business day notice. Individuals with disabilities requiring auxiliary aids or services should contact Tiffany Oliphant, communications manager, by phone (734) 327-6646 or by email [email protected].

ISSUE DATE: 01/18/24

July 17, 2023 Project Update #2: Construction Starting in 2024

During the 2024 construction season, the Washtenaw County Road Commission (WCRC) plans to construct a roundabout at the intersection of Miller Rd and Zeeb Rd in Scio Township. The intersection will be closed to all traffic during construction and a detour will be posted.

Thank you to those who were able to attend our virtual public design information meeting on Thursday, July 13, 2023. If you weren’t able to join us, click here to watch the meeting recording or check out the slide show. WCRC plans to hold a construction information meeting closer to the start of construction. WCRC will continue to send out updates as the project progresses.

Questions about the project? Contact Michele Ford, project manager, at (734) 327-6652, or via email at [email protected].

Pictured above is the planned design of the roundabout that will be constructed at the intersection of Miller Rd and Zeeb Rd in Scio Township.
June 14, 2023 Virtual Public Meeting: Miller Rd at Zeeb Rd Roundabout

PROJECT: Miller Rd at Zeeb Rd Roundabout Project

WHEN: Thursday, July 13, 2023, at 11 a.m.

WHERE: Online: https://bit.ly/wcrcprojectmeeting

By Touchtone Phone: (929) 205-6099, Meeting ID: 879 2332 8754

WHY: The Washtenaw County Road Commission (WCRC) will hold a virtual design information meeting regarding the planned roundabout project at Miller Rd and Zeeb Rd in Scio Township.

During construction, the intersection of Miller Rd and Zeeb Rd will be closed to all traffic and a detour will be posted.

The virtual public meeting will be held via Zoom on Thursday, July 13, 2023, at 11 a.m. There will be a brief presentation followed by time for questions from the audience. A recording of the meeting will be posted to the project web page after the meeting.

Click here to learn more about joining the virtual meeting.

CONTACT: If you have any questions concerning this project, please contact Michele Ford, project manager, at (734) 327-6652, or via email at [email protected].

WCRC will provide necessary reasonable auxiliary aids and services, such as signers for the hearing impaired and audiotapes or printed material being presented at the meeting, to individuals with disabilities upon a 5-business day notice. Individuals with disabilities requiring auxiliary aids or services should contact Tiffany Oliphant, communications manager, by phone (734) 327-6646 or by email [email protected].

ISSUE DATE: 06/14/23

February 13, 2023 Project Update #1: Roundabout Planned in 2024

The Washtenaw County Road Commission (WCRC) received a federal safety grant through the Highway Safety Improvement Program from the Michigan Department of Transportation (MDOT) in the fall of 2022, for a single-lane roundabout at the intersection of Miller Road and Zeeb Road in Scio Township.

WCRC routinely monitors county intersections and crash data. Based on traffic and safety studies at Miller Rd and Zeeb Rd, WCRC has determined the intersection is a candidate for this safety improvement. This intersection has a history of serious crashes and research shows that roundabouts reduce the number of severe injury or “T-bone” crashes. The installation of a roundabout at this location will improve safety and reduce the number of dangerous conflict points while maintaining traffic through the intersection.

WCRC is still in the preliminary engineering phase for the roundabout and will have a public information meeting during the design phase. Construction is anticipated to begin in 2024. While the design is ongoing, it is expected, the Miller Rd at Zeeb Rd roundabout project will look similar to the Liberty Rd at Zeeb Rd roundabout. We expect the total cost of the project to be an estimated $1.5 million.

WCRC will continue to update the project as information becomes available, and residents can click here to sign up for project updates. If you have specific questions, contact Michele Ford, project manager, at (734) 327-6652, or via email at [email protected].