Metty Dr

Location of roadwork:
Metty Dr north of Jackson Rd

Township:
Scio

When is the work being done:
2024

Description of work:
Pulverize & Rehabilitate

Impact on Traffic:
Lane Restrictions and Flagging Operation

Funding Source(s):
Michigan Transportation Fund (MTF), Scio Township Downtown Development Authority

Latest Updates

October 16, 2024 Project Update #3: Metty Dr (Scio Twp)

This week, the contractor for the Washtenaw County Road Commission (WCRC) laid the final layer of hot mix asphalt on Metty Dr. between Jackson Rd and the cul-de-sac in Scio Township.  Crews recently placed aggregate stone shoulders.  

Have any questions about this project contact Mike Bernbeck, Project Manager – Design & Construction, (734) 327-6654, or via email at [email protected] 

Pictured above new pavement on Metty Dr between Jackson Rd and the cul-de-sac in Scio Township. 
October 2, 2024 Project Update #2: Metty Dr (Scio Twp)

The contractor for the Washtenaw County Road Commission (WCRC) are crushing and shaping (pulverizing) the existing surface on Metty Dr. between Jackson Rd and the cul-de-sac in Scio Township. They will start placing the leveling course (first layer) of asphalt and the wearing course (top layer) of asphalt, this week. All work is weather permitting.  

The Washtenaw County Road Commission (WCRC) will continue to send out updates as the project progresses. Have questions? Contact Mike Bernbeck, Project Manager – Design & Construction, (734) 327-6654, or via email at [email protected] 

Pictured above pulverize pavement on Metty Dr between Jackson Rd and the cul-de-sac in Scio Township. 
September 23, 2024 Lane Restrictions: Metty Dr (Scio Twp)

WHEN: Monday, September 30, 2024

WHERE: Metty Dr between Jackson Rd and the cul-de-sac in Scio Township

WHY: Road resurfacing

BACKGROUND: On Monday, September 30, 2024, the Washtenaw County Road Commission (WCRC) will begin a resurfacing project on Metty Dr between Jackson Rd and the cul-de-sac in Scio Township.

The road will not be closed to traffic, but delays are likely due to daily lane restrictions.

The road improvements are expected to take approximately two weeks to complete. However, all dates are tentative and subject to change due to weather conditions.

CONTACT: If you have any questions concerning this work, please contact Mike Bernbeck, Project Manager – Design & Construction, (734) 327-6654, or via email at [email protected]

ISSUE DATE: 09/23/24

September 20, 2024 Project Update #1: Metty Dr (Scio Twp)

The week of Monday, September 30, 2024, a contractor for the Washtenaw County Road Commission (WCRC) is scheduled to begin resurfacing Metty Dr between Jackson Rd and the cul-de-sac in Scio Township.

Motorists can anticipate lane restrictions while the contactor is crushing and shaping the existing road, placing the leveling course (first layer) of asphalt and the wearing course (top layer) of asphalt throughout the project limits, weather permitting.  The final phase is placing aggregate (stone) shoulders and pavement markings. The project is expected to take approximately two weeks to complete.

The Washtenaw County Road Commission (WCRC) will continue to send out updates as the project progresses. Have questions? Contact Mike Bernbeck, Project Manager – Design & Construction, (734) 327-6654, or via email at [email protected].

Pictured above old pavement on Metty Dr between Jackson Rd and the cul-de-sac in Scio Township.
Contact information:
Felix Weber-Bailey
    • (734) 327-6689