Dexter-Pinckney Rd

Location of roadwork:
Dexter-Pinckney Rd between N Territorial Rd and the County Line

Township:
Dexter

When is the work being done:
2025

Description of work:
Mill & Resurfacing

Impact on Traffic:
Flagging

Funding Source(s):
Federal, Michigan Department of Transportation, Michigan Transportation Fund (MTF)

Latest Updates

November 17, 2025 County-wide Road Resurfacing-Survey

Thank you for subscribing to receive email updates about the Washtenaw County Road Commissions County-wide Road Resurfacing projects.

We are always seeking ways to improve our communications and we need your feedback. Please complete this short survey and let us know how we did communicating about road resurfacing projects. Click here for the survey.

Thank you again for subscribing and continue to follow our updates!

If you would like to subscribe to receive other road updates from us, for example, road closure alerts, click here to update your email preferences.

October 17, 2025 Project Update #3: Dexter-Pinckney Rd Resurfacing (Dexter Twp)

On Friday, October 3, 2025, Cadillac Asphalt, a Michigan Department of Transportation contractor working on behalf of the Washtenaw County Road Commission (WCRC), began the second phase of the road improvements on Dexter-Pinckney Rd in Dexter Township. The contractor milled (removed) the top surface of existing asphalt on Dexter-Pinckney Rd between McGregor Rd and the Livingston County line. On October 8, 2025, crews began the asphalt resurfacing and completed paving by the end of the day. 

Coming soon: The contractor will be completing shoulders, centerline rumble strips, and pavement markings. 

If you have questions, contact Kevin Dubnicki, Project Manager – Design & Construction, (734) 327-6693, or via email at [email protected].    

Pictured above is the new pavement on Dexter-Pinckney Rd between McGregor Rd and the Livingston County line. 
October 6, 2025 Project Update #2: Dexter-Pinckney Rd Resurfacing (Dexter Twp)

The week of September 23, 2025, PK Contracting (PK), a contractor working on behalf of the Washtenaw County Road Commission (WCRC) installed centerline corrugations (rumble strips) along Dexter-Pinckney Rd between N. Territorial Rd and McGregor Rd in Dexter Township. Following completion of rumble strips, PK subsequently completed applying the pavement markings on this stretch of road, including intersection markings at North Territorial Rd. 

If you have questions, contact Felix Weber, Project Manager – Design & Construction, (734) 327- 6689, or via email at [email protected]. 

Pictured above is of PK Contracting adding centerline corrugations (rumble strips) along DexterPinckney Rd between N. Territorial Rd and McGregor Rd in Dexter Township. 

October 1, 2025 Lane Restrictions: Dexter-Pinckney Rd (Dexter Twp)

WHEN: Friday, October 3, 2025

WHERE: Dexter-Pinckney Rd between McGregor Rd and the County Line in Dexter Township

WHY: Mill & resurfacing

BACKGROUND: On Friday, October 3, 2025, a contractor for the Washtenaw County Road Commission (WCRC) will begin mill and resurfacing on Dexter-Pinckney Rd between McGregor Rd and the County Line in Dexter Township.

The road improvements are expected to take approximately four weeks to complete. However, all dates are tentative and subject to change due to weather conditions.

The road will not be closed to traffic, but delays are likely due to lane restrictions. WCRC encourages motorists, emergency services and others to use an alternate route.

CONTACT: If you have any questions concerning this closure, please contact Kevin Dubnicki, Project manager, (734) 327-6693, or via email [email protected]

ISSUE DATE: 10/01/25

September 25, 2025 Revised Intermittent Lane Restrictions: Dexter-Pinckney Rd (Dexter Twp)

WHEN: Tuesday, September 23, 2025

WHERE: Dexter-Pinckney Rd between N. Territorial Rd and McGregor Rd in Dexter Township

 WHY: Centerline corrugation (rumble strips) & pavement markings

 BACKGROUND: Tuesday, September 23, 2025, the Washtenaw County Road Commission (WCRC) started adding centerline corrugation (rumble strips) and pavement markings at Dexter-Pinckney Rd between N. Territorial Rd and McGregor Rd in Dexter Township.

The roadwork has been extended and is expected to take approximately 5 days to complete.

The road will not be closed to traffic, but delays are likely due to intermittent lane closures and lane restrictions. WCRC encourages motorists, emergency services and others to use an alternate route.

CONTACT: If you have any questions concerning this work, please contact Felix Weber, Project Manager, (734) 327-6689, or via email at [email protected]

ISSUE DATE: 09/25/25

September 22, 2025 Intermittent Lane Restrictions: Dexter-Pinckney Rd (Dexter Twp)

WHEN: Tuesday, September 23, 2025 

WHERE: Dexter-Pinckney Rd between N. Territorial Rd and McGregor Rd in Dexter Township 

WHY: Centerline corrugations & pavement markings 

BACKGROUND: Tuesday, September 23, 2025, the Washtenaw County Road Commission (WCRC) will be adding centerline corrugation (rumble strips) and pavement markings on Dexter-Pinckney Rd between N. Territorial Rd and McGregor Rd in Dexter Township.

This mobile operation is expected to take approximately 2 days to complete.

The road will not be closed to traffic, but delays are likely due to intermittent lane closures and lane restrictions. The WCRC encourages motorists, emergency services and others to use an alternate route.

CONTACT: If you have any questions concerning this work, please contact Felix Weber, Project Manager, (734) 327-6689, or via email at [email protected]

 ISSUE DATE: 09/22/25

September 10, 2025 Project Update #1: Dexter-Pinckney Rd Resurfacing (Dexter Twp)

During the week of August 18th, a contractor working on behalf of the Washtenaw County Road Commission (WCRC) applied longline pavement markings (striping) on Dexter Pinckney Rd between N. Territorial Rd and McGregor Rd in Dexter Township. 

This pavement marking operation followed the earlier asphalt resurfacing of the road. 

Next Steps: During the week of September 8th, centerline corrugations (rumble strips) will be installed in this newly paved primary county road segment. This will promote motorist safety, reducing the potential for “crossover” vehicle crashes. 

This work is funded by the 2025-2028 Roads and Non-Motorized Millage, supported by a vote of the Washtenaw County public in the fall of 2024. 

If you have questions, contact Felix Weber, Project Manager – Design & Construction, (734) 327- 6689, or via email at [email protected].   

Pictured above is a photo of the contractor paving on Dexter-Pinckney Rd. 
Pictured above are newly installed pavement markings on Dexter-Pinckney Rd. 
August 5, 2025 Intermittent Lane Restrictions: Dexter Pinckney Rd (Dexter Twp)

WHEN: Friday, August 8, 2025

WHERE: Dexter Pinckney Rd between N. Territorial Rd and McGregor Rd in Dexter Township

WHY: Milling and resurfacing

BACKGROUND: On Friday, August 8, 2025, the Washtenaw County Road Commission (WCRC) will be milling and resurfacing on Dexter Pinckney Rd between N. Territorial Rd and McGregor Rd in Dexter Township.

The road will not be closed to traffic, but delays are likely due to intermittent lane restrictions. WCRC encourages motorists, emergency services and others to use an alternate route.

The road improvements are expected to be completed in seven days. However, all dates are tentative and subject to change due to weather conditions.

CONTACT: If you have any questions concerning this work, please contact Felix Weber, Project Manager, (734) 327-6689 or via email at [email protected].

ISSUE DATE: 08/05/25

February 4, 2025 Virtual Public Meeting: 2025 Resurfacing Program (County-wide)

WHEN: Friday, February 14, 2025, at 11 a.m.

WHERE: Online: https://bit.ly/wcrcprojectmeeting

By Touchtone Phone: (929) 205-6099, Meeting ID: 879 2332 8754

WHY: The Washtenaw County Road Commission (WCRC) will hold a virtual project information meeting regarding the planned County-wide Resurfacing Program taking place during the 2025 construction season.

During construction, traffic will be maintained under lane restrictions and flagging operations. During specific construction activities, the road may be closed, and a detour will be posted. WCRC estimates it will take approximately two/three weeks, on average, to complete each project, weather pending.

The virtual public meeting will be held via Zoom Friday, February 14, 2025, at 11 a.m. There will be a brief presentation followed by time for questions from the audience. A recording of the meeting will be posted to the project web page after the meeting.

Click here to learn more about joining the virtual meeting.

CONTACT: If you have any questions concerning these project, please contact Felix Weber-Bailey, Project Manager, (734) 327-6654, email [email protected], Kevin Dubnicki, Project Manager, (734) 327 -6693, email [email protected] and Ken Harris, Superintendent, (734) 327-6696, email [email protected]

WCRC will provide necessary reasonable auxiliary aids and services, such as signers for the hearing impaired and audiotapes or printed material being presented at the meeting, to individuals with disabilities upon a 5-business day notice. Individuals with disabilities requiring auxiliary aids or services should contact Tiffany Oliphant, communications manager, by phone (734) 327-6646 or by email [email protected].

ISSUE DATE: 02/04/25

February 4, 2025 Project Announcement: 2025 Resurfacing Program (County-wide)

The Washtenaw County Road Commission (WCRC) is excited to announce a $9.4 million investments in improving approximately 37 miles of paved and unpaved roads across Washtenaw County during the 2025 construction season. These important projects are made possible through a combination of funding sources, including the 2025-2028 Four-Year County-Wide Roads and Non-motorized Millage, Federal Funds, Township partnerships, and Michigan Transportation Funds (MTF). 

 “This year’s resurfacing program is just one of the ways WCRC is committed to protecting the county’s transportation infrastructure,” said Brent Schlack, P.E., Director of Engineering and County Highway Engineer. “The successful completion of these critical projects requires a blend of resources and collaboration.” 

 Construction is slated to begin in mid-April and will continue through the fall of 2025, weather permitting. As part of this program, WCRC will also undertake necessary forestry work to maintain the safety and integrity of the roadways. 

 For a list of the specific projects, funding details, and anticipated traffic impacts, please refer to the links provided below for each project location. 

Motorists will experience road closures with detours, daytime road closures, lane restrictions, and flagging operations. WCRC will maintain access for residents who live or work within the project limits during construction. 

WCRC will host a virtual public information meeting regarding the County-wide Resurfacing projects on February 14, 2025. WCRC will post project updates online at wcroads.org. Residents can subscribe to road work advisories and project updates here.

For specific questions on these projects, contact Felix Weber-Bailey, Project Manager, (734) 327-6654, email [email protected], Kevin Dubnicki, Project Manager, (734) 327 -6693, email [email protected] and Ken Harris, Superintendent, (734) 327-6696, email [email protected] 

Pictured is a map of our 2025 County-wide Resurfacing Program.

Contact information:
Felix Weber
    • (734) 327-6689
Receive Updates on the Project
Subscribe to Project Updates
Washtenaw County Road Commission
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.