Project Update #3: Dexter-Pinckney Rd Resurfacing (Dexter Twp)

By October 17, 2025Project Updates

On Friday, October 3, 2025, Cadillac Asphalt, a Michigan Department of Transportation contractor working on behalf of the Washtenaw County Road Commission (WCRC), began the second phase of the road improvements on Dexter-Pinckney Rd in Dexter Township. The contractor milled (removed) the top surface of existing asphalt on Dexter-Pinckney Rd between McGregor Rd and the Livingston County line. On October 8, 2025, crews began the asphalt resurfacing and completed paving by the end of the day. 

Coming soon: The contractor will be completing shoulders, centerline rumble strips, and pavement markings. 

If you have questions, contact Kevin Dubnicki, Project Manager – Design & Construction, (734) 327-6693, or via email at [email protected].    

Pictured above is the new pavement on Dexter-Pinckney Rd between McGregor Rd and the Livingston County line.