Wagner Rd: Pave the Day

By September 8, 2021Project Updates

We continue to make great progress for the Wagner Rd Safety Project at the intersection of Wagner Rd and Waters Rd in Lodi Township.

Last week our contractor poured the concrete for the new curb and graded the road base for the new turn lane. This week our contractor plans to pave the first layer of asphalt for the new turn lane. Once completed they will begin to mill the existing asphalt for the remainder of the intersection before repaving and applying a seal coat.

While all this is great news, we do expect the road closure to last until the end of the September now due to some scheduling issues from weather and contractor availability.

If you have any questions concerning this work, please contact Elena Yadykina, engineer – Traffic and Safety, (734) 327-6675, yadykinae@wcroads.org.

photo of the new concrete curb

Pictured above is the new concrete curb at the intersection of Wagner Rd and Waters Rd.