US-12 and M-17 Improvements: Construction Info Meeting Follow-up

Thank you to those who were able to join OHM yesterday for a virtual construction information meeting regarding the US-12 and M-17 Improvement Project. Click here to watch a recording of last night’s meeting.

Starting this Monday, June 7, the contractor for this project will begin removing the fly-over bridge from Ecorse Rd to eastbound US-12. To keep motorists safe during the removal, they will close a portion of westbound US-12 that travels under the bridge and a detour will be posted.  The closure is expected to last approximately 2 weeks.

Click here for the detour map.

Questions about this project?  Contact Thomas Bachmayer, OHM project engineer, (734) 466-4422, thomas.bachmayer@ohm-advisors.com.