Our contractor continues to make steady progress on the Saline-Milan Road Bridge Replacement Project in York Township. This week they are working on the northern abutment, another necessary step before they can have a dry platform to build the bridge substructure. Meanwhile, a subcontractor is installing the soldier piles for the retaining wall on the easterly side of the road (see below).

If you have questions about the bridge project, please contact Nate Murphy, bridge engineer, [email protected] or (734) 327-6647.

 Drone view of the bridge progress

Washtenaw County Road Commission
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.