Shield Rd Bridge – Progress Update

Over the last 3 weeks, the contractor has constructed the east bridge foundation and began placing sand fill around it.  The cofferdam for the west bridge foundation was completed, soil was excavated and the foundation pile driving has begun.

Washtenaw County Road Commission
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.