Ridge Rd Bridge – Progress Update

By August 11, 2017Project Updates

Over the last 3 weeks, the contractor completed the bridge removal, completed the cofferdam installation for the south bridge foundation, excavated soil within the cofferdam and began driving the foundation piling necessary for structural support of the bridge.