Project Update Dennison Rd: We Dig It!

By March 25, 2021Project Updates

Our contractor is digging the progress they are making on Dennison Rd. The last of the trees that needed to be cleared have been removed. The southern bridge span, internal supports, and end supports have also been removed. The contractor will be completing the excavation for the new substructure and will begin installation of the steel H piles starting later today, which will support the southern substructure of the bridge.

Questions? Contact Nate Murphy, project manager, (734)-327-6647, [email protected] 

Washtenaw County Road Commission
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.