Project Update Dennison Rd: Out with the old, in with the new

By April 7, 2021Project Updates

We are officially 4 weeks into construction on the Dennison Rd bridge, and our contractor continues to make good progress. The northern internal supports of the old bridge have been removed, and the removal of the northern end supports will continue. The structural support for the new bridge is being welded, and once completed will be pounded into the ground to offer a deep foundation for the new structure.

Questions? Contact Nate Murphy, project manager and bridge engineer, (734) 327-6647, murphyn@wcroads.org.