Project Update Dennison Rd: It’s All About The Base

By May 5, 2021Project Updates

The past couple weeks at the Dennison Rd Bridge we have been busy creating the base for the new bridge. Last week, our contractor poured the concrete at the southern end of the bridge, and now that the concrete has cured, the forms have been removed and they started backfilling behind it. The northern end support of the bridge is also progressing as the piles have been completed and the forms, for the concrete pour, are being set. In the coming weeks, the concrete at the northern end will be poured.

Questions? Contact Nate Murphy, project manager and bridge engineer, (734) 327-6647, [email protected].