Project Update: Construction Is Soon Underway!

During the 2023 construction season, the Washtenaw County Road Commission (WCRC) plans to replace a culvert on Parker Rd between Shield Rd and Dexter-Chelsea Rd in Lima & Scio Townships. The exact start date of the construction is still yet to be determined. During construction, Parker Rd will be closed to all traffic and a detour route will be posted. This closure is expected to be in place for approximately seven weeks, weather pending.

Thank you to those who were able to attend our virtual public meeting on Thursday, May 18, 2023. If you weren’t able to join us, click here to watch the meeting recording or check out the slide show. WCRC will send out updates as the project progresses.

Questions about the project? Contact Nate Murphy, project manager, at (734) 327-6647, or via email at [email protected].

Pictured above is the culvert that will be replaced on Parker Rd between Shield Rd and Dexter-Chelsea Rd in Lima & Scio Townships.