Project Update: Construction Is Moving Along!

Construction of the Platt Rd Greenway II Pathway project in Pittsfield Township is moving along!  

The contractor has completed the mainline storm sewer and has graded the projected pathway. Currently, the contractor is stripping topsoil in preparation for placing the aggregate base for the asphalt pathway.  

Residents can expect to see intermittent lane restrictions on Platt Rd between Wall Park and Waterfowl Blvd while the pathway is being constructed. The Washtenaw County Road Commission (WCRC) will continue to send out updates as the project progresses.    

Questions about the project? Contact Chris Brinks, project engineer, at (734) 947-2788, or via email at [email protected]

Pictured above is the mainline storm sewer that was recently installed near Platt Rd between Wall Park and Waterfowl Blvd in Pittsfield Township