Project Update: Close to the Finish Line!

By November 6, 2023Project Updates

We’re getting close to the finish line on our Platt Rd Greenway II non-motorized pathway project near Platt Rd, between Wall Park and Waterfowl Blvd in Pittsfield Township.  

Last week, the contractor placed mast arms at the crosswalks at Wall Park and Platt Rd, as well as Platt Rd and Waterfowl Blvd. The contractor is tentatively scheduled to return November 12, 2023, to complete the installation. The pathway is open for pedestrian use but there will be intermittent closures during the crosswalk installation work.  

The Washtenaw County Road Commission (WCRC) will continue to send out updates as the project progresses. Have questions about the project? Contact Chris Brinks, project engineer, at (734) 647-2788, or via email at [email protected]     

Pictured are the mast arms that were installed at the crosswalks at Wall Park and Platt Rd, and Waterfowl Blvd and Platt Rd, both in Pittsfield Township.