The week of September 16, the contractor for the Washtenaw County Road Commission (WCRC) has excavated and placed the bedding stone in preparation for the placement of the new structure on the Stony Creek Rd over Paint Creek between Textile Rd and Whittaker Rd in Ypsilanti Township. The new precast concrete structure is anticipated to be delivered the week of September 23rd. All work is weather permitting.
It’s important to remember that Stony Creek Rd is closed between Textile and Whittaker Rd. Here is a link to the official detour.
WCRC will send out updates as the project progresses. Have any questions about the project? Contact Neeko Robison, Project Manager – Design & Construction, at (734) 327-6660, or via email at [email protected].

Pictured is the bridge bedding on Stony Creek Rd over Paint Creek between Textile Rd and Whittaker Rd in Ypsilanti Township.