Project Update #5: Cherry Hill Rd Bridge Replacement (Superior Twp)

By August 6, 2026Project Updates

During the end of July, the contractor working on behalf of the Washtenaw County Road Commission (WCRC) constructed the concrete curb and road approaches to the Cherry Hill Rd Bridge, between Gale Rd and Plymouth Rd, in Superior Township. The contractor has completed asphalt paving and installed guardrails 

Final clean-up and restoration efforts are underway, including planned pavement markings on August 7th and an anticipated open-to-traffic date of August 8th. 

Cherry Hill Rd is currently closed to all traffic; please follow the detour signs. 

For specific questions regarding this project, contact Kevin Dubnicki, Project Manager, at (734) 327-6693, or via email at [email protected]. 

Pictured above is the nearly completed Cherry Hill Rd Bridge in Superior Township.  
Washtenaw County Road Commission
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.