The week of August 10, the contractor installed wingwall anchors and began backfilling over the new culvert on Warner Rd between Jewell Rd and Judd Rd in York Township. Additionally, they released the construction dam and opened the stream to flow freely through the new structure. This week, the contractor will grade Warner Rd and install the guardrail.
Warner Rd remains closed between Jewell Rd and Judd Rd. The detour will continue to be in effect, and motorists are advised to follow this route for the duration of the project.
If you have any questions regarding this project, contact Neeko Robison, Project Manager, at (734) 327-6660 or [email protected]

Pictured above is the new box culvert after being placed on Warner Rd between Jewell Rd and Judd Rd in York Township.

Pictured above is the new box culvert being backfilled on Warner Rd between Jewell Rd and Judd Rd in York Township.