By November 20, 2026Project Updates
Demolition Complete

Demolition of the existing bridge is complete on Sharon Valley Rd over the River Raisin, between Sharon Hollow Rd and Meyers Rd in Sharon Township. A Washtenaw County Road Commission (WCRC) contractor has placed engineered fill to induce settlement of the underlying soils prior to construction of the new bridge and road approaches. This process will take approximately 4 months and then construction will resume.

Next Steps:

  • Construction is anticipated to resume in the Spring 2027. The actual start date will be determined based on settlement monitoring by the contractor.

Sharon Valley Rd remains closed to all traffic; please follow the detour signs. WCRC will provide ongoing updates.

For specific questions regarding this project, contact Kevin Dubnicki, Project Manager, at (734) 327-6693, or via email at [email protected].

Pictured above is facing east towards the old bridge on Sharon Valley Rd over the River Raisin, between Sharon Hollow Rd and Meyers Rd in Sharon Township.

Pictured above is facing west towards the old bridge on Sharon Valley Rd over the River Raisin, between Sharon Hollow Rd and Meyers Rd in Sharon Township.

Washtenaw County Road Commission
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.