Project Update #4 – Cherry Hill Rd Bridge Replacement (Superior Twp)

By July 27, 2026Project Updates

During the middle weeks of July, the contractor working on behalf of the Washtenaw County Road Commission (WCRC), stripped forms for the bridge and is allowing the bridge deck to cure and gain strength. This week the contractor is working on stripping forms and preparing to grade the HMA approach. 

Next Steps: 

  • Curb installation and finalize approach slabs 
  • HMA paving to occur end of the week of July 27th  

Cherry Hill Rd remains closed to all traffic; please follow the detour signs. WCRC will provide ongoing updates. 

For specific questions regarding this project, contact Kevin Dubnicki, Project Manager, at (734) 327-6693, or via email at [email protected] 

Pictured above is the south approach to the Cherry Hill Rd bridge, over Fleming Creek, in Superior Township. Concrete was poured July 24th 
Washtenaw County Road Commission
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.