The installation of new bridge beams and steel reinforcement has been completed on the Cherry Hill Rd Bridge over Fleming Creek, between Gale Rd and Plymouth Rd in Superior Township. Recently, the contractor working on behalf of the Washtenaw County Road Commission (WCRC) completed the concrete work for the bridge approaches and poured the concrete bridge deck.
Cherry Hill Rd remains closed to all traffic; please follow the detour signs. WCRC will provide ongoing updates.
For specific questions regarding this project, contact Kevin Dubnicki, Project Manager, at (734) 327-6693, or via email at [email protected].

Pictured above is the prepared steel reinforcement night pour for the Cherry Hill Rd bridge, over Fleming Creek, in Superior Township.