Project Update #2: Waterloo Rd (Lyndon Twp)

By September 20, 2024Project Updates

This week, the contractor completed the resurfacing project on Waterloo Rd between Clark Lake Rd and Lingane Rd in Lyndon Township. Next week, the contractor will place the aggregate (stone) shoulders and pavement markings on a newly paved Waterloo Rd.

If you have questions about this project contact Mike Bernbeck, Project Manager – Design & Construction, (734) 327-6654, or via email at [email protected].

Pictured above is a newly resurfaced Waterloo Rd between Clark Lake Rd and Lingane Rd in Lyndon Township.