The contractor working on behalf of the Washtenaw County Road Commission (WCRC) is stripping topsoil and forming ditches along the sides of Scio Church Rd and Zeeb Rd in Lodi and Scio Townships. The ditching is in preparation for the storm sewer installation that will occur during the week of July 6th.
The intersection of Scio Church Rd at Zeeb Rd remains closed to all traffic. Motorists are encouraged to follow the posted detour. All truck traffic is to follow the detour using Pleasant Lake Rd and Wagner Rd.
WCRC will continue to send out updates as the project progresses.