Project Update #2: Parker Rd Resurfacing (Lima & Scio Twps)

By April 30, 2024Project Updates

Construction is quickly moving along for the resurfacing project on Parker Rd between Scio Church Rd and Liberty Rd in Lima & Scio Townships.  

Since the last update, the contractor began paving operations on Parker Rd. Once paving is completed, the next step is placing aggregate (stone) shoulders. The contractor expects to place stone shoulders by the end of this week. The Washtenaw County Road Commission (WCRC) plans to re-open the roadway once this work has been completed.  

As a reminder, Parker Rd remains closed to all through traffic. Access is only maintained for residents who live or work within the project limits. WCRC will continue to send out updates as the project progresses.  

Have questions about the project? Contact Mike Bernbeck, Project Manager – Design & Construction, at (734) 327-6654, or via email at [email protected].  

Pictured is the contractor paving Parker Rd between Scio Church Rd and Liberty Rd in Lima & Scio Townships.