Project Update #2: Earhart Rd Resurfacing (Ann Arbor Twp)

By October 16, 2025Project Updates

On October 9, 2025, Cadillac Asphalt, a Michigan Department of Transportation contractor working on behalf of the Washtenaw County Road Commission, completed asphalt resurfacing (paving) the entire segment of Earhart Rd between Plymouth Rd and M-14 in Ann Arbor Township. 

The contractor has also completed installation of new guardrails at the M-14 overpass and the placement of aggregate (stone) shoulder material along the newly paved road. 

Moving forward: Traffic signal-related work (by the WCRC) and pavement markings (by the contractor) remain to be completed. 

If you have questions, contact Kevin Dubnicki, Project Manager – Design & Construction, (734) 327-6693, or via email at [email protected].      

Pictured above is the new pavement on Earhart Rd between Plymouth Rd and M-14 in Ann Arbor Township. 

Washtenaw County Road Commission
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.