Finally, paving of Segment D3 of the Border-to-Border Trail along the Huron River in Scio Township has begun!
Over the last couple of weeks, the contractor has driven steel piles for the bridge abutments and placed the base course of asphalt along some portions of the trail. Next, the contractor will be placing forms for the concrete bridge abutments to prepare for placing the pedestrian bridge. Once the bridge is set in place, asphalt paving of the remaining portions of the pathway will continue.
As a reminder, the pathway remains closed to the public. Even though there is asphalt on some portions of the trail, this location continues to be an active construction zone and is not open for public use. The Washtenaw County Road Commission (WCRC) will continue to send out updates as the project progresses.
Have questions? Contact Michele Ford, Sr. Project Manager – Traffic & Safety, at (734) 327-6652, or via email at [email protected].