Project Update #1: Sharon Valley Rd Bridge Replacement (Sharon Twp)

By February 23, 2024Project Updates

In early February, a contractor for the Washtenaw County Road Commission (WCRC) closed Sharon Valley Rd, over River Raisin, between Sharon Hollow Rd and Meyers Rd in Sharon Township for permitted soil boring (soil samples) work. The permitted work is related to preparation for the bridge replacement planned for 2025.  

Due to subsurface water issues that have been encountered during this permitted work, the closure will be extended until the WCRC contractor can finish collecting soil samples. We hope to re-open the road early next week. WCRC will continue to send out updates as the project progresses. 

For specific questions regarding this project, please contact Nate Murphy, Senior Project Manager – Design & Construction, at (734) 327-6647, or via email at [email protected]. 

Pictured is contractor collecting soil samples on Sharon Valley Rd, over River Raisin, between Sharon Hollow Rd and Meyers Rd in Sharon Township. 
Washtenaw County Road Commission
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.