Our resurfacing project on Miller Rd between Wagner Rd and M-14 in Scio Township is moving along! 

On Friday, July 12, 2024, the contractor began milling and removing the existing road surface. Paving operations have been delayed due to weather conditions. However, the contractor expects to begin paving later this week. Once paving is completed, the next step will be placing aggregate (stone) shoulders and pavement markings.  

The Washtenaw County Road Commission (WCRC) will continue to send out updates as the project progresses. Have questions? Contact Mike Bernbeck, Project Manager – Design & Construction, (734) 327-6654, or via email at [email protected].  

Pictured above are the milling operations that took place on Miller Rd between Wagner Rd and M-14 in Scio Township.