Project Update #1: Joy Rd Culvert Replacement (Webster Twp)

By September 24, 2025Project Updates

Project Progressing 

On Tuesday, September 23, 2025, the Washtenaw County Road Commission (WCRC), began removing and replacing the culvert on Joy Rd between Jennings Rd and Stein Rd in Webster Township. 

Crews have started to build the box culvert and will start excavating and removing the old culvert this week.  

Next week, crews will be finishing backfilling, installing headwalls and restoration. Once the project is complete, the road will be re-opened to traffic. WCRC will send out updates as the project progresses. 

WCRC is able to perform this project thanks to the American Rescue Plan Act (ARPA) and its partnership with the Washtenaw County Water Resources Commissioner’s Office and the Township.   

If you have any questions regarding this project, contact Ken Harris, Superintendent of Maintenance, at (734) 327-6696, or via email at [email protected]. 

Pictured above is the failed culvert before the work began on Joy Rd between Jennings Rd and Stein Rd in Webster Township. 
Pictured above is the WCRC crew beginning the assembly on the box culvert to be placed under Joy Rd between Jennings Rd and Stein Rd in Webster Township. 
Washtenaw County Road Commission
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.