On June 24, 2026, the contractor working on behalf of the Washtenaw County Road Commission (WCRC) began milling (removing) the existing road surface on Grass Lake Rd between Sylvan Rd and M-52 in Sharon Township. The milling was completed on June 25th, with asphalt paving starting the next day. On June 30th, the contractor completed the paving of Grass Lake Rd between Sylvan Rd and M-52 in Sharon Township with a new asphalt surface.
In the coming weeks, new permanent pavement markings will be added to the freshly paved surface.
If you have questions, contact Felix Weber, Project Manager, (734) 327-6689, or via email at [email protected].

Pictured above are milling operations on Grass Lake Rd between Sylvan Rd and M-52 in Sharon Township.

Pictured above is asphalt paving on Grass Lake Rd between Sylvan Rd and M-52 in Sharon Township.