Project Update #1: Dexter-Chelsea Rd Resurfacing (Lima Twp)

By August 5, 2024Project Updates

Our asphalt resurfacing project on Dexter-Chelsea Rd between Dancer Rd and Parker Rd in Lima Township is quickly moving along… 

On Wednesday, July 31, 2024, the Michigan Department of Transportation (MDOT) contractor milled joints at the beginning and ending points of the project. On Saturday, August 3, 2024, the contractor started paving operations. Unfortunately, paving operations have been delayed due to weather conditions on Monday, August 5. The contractor hopes to complete paving by the end of this week. Once paving is finished, aggregate (stone) shoulders and permanent pavement markings will be placed.  

WCRC will send out updates as the project progresses. Have questions about the project? Contact Becky Houle, Project Manager – Traffic & Safety, at (734) 327-6678 or via email at [email protected] 

Pictured above is the new surface being place for Dexter-Chelsea Rd between Dancer Rd and Parker Rd in Lima Township.