Our contractor is planning to pave the first layer of asphalt on Textile Road between Campbell Road and Platt Road later this week, if the weather cooperates.

This first layer will cap the gravel and grading work that has already been completed, protecting the roadbed from weather and construction traffic. Once this first layer has been installed, our contractor will focus on building the pathway. The plan is to substantially complete the pathway before paving the final two layers of asphalt on the road later this summer.

WCRC still expects the project to be completed by the end of July. As a reminder, Textile Road remains closed to ALL traffic from the Thomas Road intersection to just west of Platt Road in Pittsfield Township.

If you have any questions concerning this work, please contact Mark McCulloch, project manager, (734) 327-6679, or via email at mccullochm@wcroads.org

For more information about this project, visit www.wcroads.org/wcrc-project/textile-road-3/