Our contractor continues to make good progress on the reconstruction of the intersection of Ridge Road and Hack Road in York Township. The paving subcontractor was on site earlier this week paving the first layer of asphalt pavement. They will be back soon to pave the second layer of asphalt.

Some work remains before the intersection can be reopened to traffic, including, the installation of concrete truck aprons and applying the high-friction surface application to help keep vehicles on the road. We are hoping to have the intersection reopened to traffic by the first week of November, as long as the weather continues to cooperate.

If you have any questions, please contact Aaron Berkholz, senior project manager, (734) 327-6648, [email protected]

Our paving subcontractor completed the first layer of asphalt earlier this week.