Pause in the Ann Arbor-Saline Road Action

By November 15, 2019Project Updates

As you know, we were very pleased to reopen Ann Arbor-Saline Road last Friday (one week ahead of schedule!). We have a little more cleaning up to do in this area once the snow melts, including removing any remaining detour signs. Pavement markings will be placed in the early spring. 

This will be the last project update for a few months, we will start project updates again once we get closer to the closure of the intersection of Ann Arbor-Saline Road and Wagner Road in the spring. We plan to reconstruct the intersection to include concrete pavement, drainage improvements, dedicated turn lanes, and a traffic signal. The intersection will be closed for approximately three months during this project. 

In the meantime, if you have any questions about these projects, please contact Michele Ford, project manager, (734) 327-6652, fordm@wcroads.org