Moon Rd: Fresh Pavement Coming Soon!

Despite the snowy weather earlier this week, we are making great progress on the Moon Rd Resurfacing Project in York Township. Our crews were able to finish the crossroad culvert replacements and the forestry work earlier this week. Drainage improvements are still underway.

Our contractors have been pulverizing (or crushing) the existing pavement, which will be recycled and compacted to create the new road base. We are hoping to begin paving early next week, weather pending.

Questions? Contact Mike Bernbeck, project manager, (734) 327-6654, [email protected].

pictured is crushed pavement

Pictured above is the pulverized (or crushed) surface of Moon Rd. Weather pending, paving should begin early next week!