Miller/Wagner: Island Time

By September 11, 2020Project Updates

Although it was a short week with the holiday and some rain, we continue to make progress on the new Miller Road roundabout and bridge in Scio Township.

Miller/Wagner Roundabout: Our contractor is preparing the interior of the roundabout for more concrete. They will first pour the interior curb for the central island and splitter islands. Once the concrete has cured, they will pour and stamp concrete inside the islands.

Bridge Over Honey Creek: Utility relocation work continues near the Miller Road bridge over Honey Creek.

Right now, we are hoping to have the roundabout completed by mid-October and the bridge completed by early-December if the weather cooperates. Questions? Contact Nate Murphy, project manager, (734) 327-6647, [email protected].

photo of roundabout grading